Category: Blog

AQ: Variable Air Volume System Optimization

Variable Air Volume Systems (VAV) can be optimized to increase energy savings by maximizing the efficiency of the equipment at part-load conditions. The goal with the optimization strategy is to run each subsystem (chiller, cooling tower, Airhandler, etc) in the most efficient way possible while maintaining the current building load requirement.

VAV System Optimization

As each Variable Air Volume terminal controls the space temperature – based on flow – the “worst case” zone can easily be identified by an automation system. The supply fan speed can be reduced by resetting the static pressure (see following page). As the load drops and the fan meets a preset minimum flow, the system resets the air temperature up, so less chilled water is needed. In a variable flow chiller system, this reduces pumping energy.

If the system load continues to drop, the system will reset the chiller supply water temperature upward which will then reduce the energy requirements of the chiller. Changes in the chiller head pressure and loads can then reset the cooling tower fan speed.

The key to optimizing the system operation is communication and information sharing through the entire system equipment. With the reduced cost of variable frequency drives and Building Automation Systems, (BAS) complete system optimization can be implemented as a cost effective option.

In VAV systems where the individual VAV boxes and the AHU are on a building automation system, additional savings can be achieved by implementing static pressure reset. The static pressure sensor in a VAV system is typically located two-thirds of the way downstream in the main supply air duct for many existing systems. Static pressure is maintained by modulating the fan speed.

When the static pressure is lower than the setpoint, the fan speeds up to provide more airflow (static) to meet the VAV box needs, and vice-versa. A constant set point value is usually used regardless of the building load conditions.

Under partial-load conditions the static pressure required at the terminal VAV boxes may be far less than this constant set point. The individual boxes will assume a damper position to satisfy the space temperature requirements. For example, various VAV box dampers will be at different damper positions, (some at 70% open, 60% open, etc) very few will be at design, ie 95% -100% open.

RESET STRATEGY
Essentially, resetting supply air static pressure requires that every VAV box is sampled with the static reset set to the worst case box requirement. For example, each box is polled, every 5 minutes. If no box is more than 95% open, reduce duct static pressure set point by 5%. If one or more boxes exceed 95% open, increase static pressure set point by 5%.

With a lower static set point to maintain, fan speed reduces. The result is increased energy savings in the 3 to 8% range. See figure below. If the BAS system is already installed, implementing this strategy is relatively free.
Variable Air Volume System energy savings

AQ: Renewable Energy in India

Holistic and Combined i.e Hybrid Renewable Energy Generation per Taluka / District of Each state with Energy Potential study with Investment seeking proposal with land (barren) identified with Revenue department clearances and also with a clear MAP of Evacuation with existing Transmission lines and future lines to planned, which shall be appended to RfP and not ask each developer to identify the location and struggle with Government Administration (which will increase time and Costs (read wrong costs)) complying to Land Acquisition bill and also eliminate the real estate babus to relinquish 5000 acres of land per state, which is BENAMI now…..I do not know how this excess land in BENAMI exist when we have Land ceiling Act!!

In order to do an extensive and credible study to explore renewable energy potential in each Taluka, State and Central Government Can hire international Consultancies with Video Documentation with GPRS MAPS to know the real truth and there shall not be much difference between reports and the ground reality, otherwise, hold these agencies responsible with necessary punitive clauses.

These costs can be recovered in the form of Bid document charges, which any serious developer will pay. However, the Equity selling proxy promoters, who have access to the power corridor and bid with Net worth Financial capacity, but, not worthy of any Renewable energy promotion as we saw in JNNSM wherein a large corporate bought equity from the other bidders and later an investigation took place…..

Following is the excerpts of the Mail written to MNRE and KREDL, in Jan 2012 (now we see their web site showing Biomass study is under progress):

For Power evacuation, we need to know the following (as we can’t use the existing data):

a). Distance from the Power generation site, which normally comes under KREDL (single window agency) i.e where one can put up the plant by undergoing NA or KREDL has identified land bank in Yadgir, but, how many km is the Substation from these sites, which we verified, was difficult to ascertain due to patch lands and the distance was over 10 km in certain cases.

b). Whether these substations can accept 20 MW or 10 MW or 5 MW of intermittent Solar PV load (non firm power which at times may create grid related disturbances etc). Biomass power is firm power as long as Firm biomass feed stock is available.

Therefore, we have been writing to many agencies involved to come out with a common approach, wherein the bidding documents identify clearly the SLDCs where the Project Developer can upload (evacuate) the energy generated with an in principle approval (with location MAP with transmission distances etc) from SLDC and ESCOM to accept such Renewable energy as the States are bound to buy the RE under RPO.

If the investor or RE Generator has to run around to know the fundamentals, then, please try to imagine how many man hours will be wasted and how much money gets drained from many participants for the same location? Instead, these data is available with KPTCL / KREDL / KERC / ESCOMs or such multiple organisation, but, Single window agency KREDL does not produce such VITAL information in their bid documents, hence, we as entrepreneurs are trying to tie the loose ends and make things happen for the good of our state.

I hope you understand our concern and append the finer details of evacuation, project site, land bank, the maximum capacity of MWh the substation can take or any upgrade is needed etc be appended in the bidding documents or even in your web sites also.

Further, any new substations are under development, the same with a clearly identified MAP with distances will help the people to understand the grid network to ensure the grid sustainability, reduction in transmission lines and hence the losses can be planned while making the bids, which otherwise will be a

AQ: Frequency Inverter Direct Digital Control

Modulating Supply & Return Fans are used as a means of providing proper variable air volume (VAV) control as well as building pressurization. Many such VAV systems are still largely pneumatic with static to the downstream boxes being maintained by inlet guide vanes. To provide increased energy savings and energy comfort, these systems can be easily converted to frequency inverter fan control of the supply and return fans and Direct Digital Control (DDC) to coordinate any increased energy saving strategies. Figure 1 shows such a system.

Frequency Inverter Direct Digital Control

To increase energy savings, the DDC controller can be programmed to reduce the flow from the return & supply fans for short periods of time. Coordinated with the building pressurization system, any temporary loss of space temperature may be avoided.

In Figure 1, the supply fan is controlled by the duct static pressure sensor, via the DDC, while the outside air and mixed air dampers are optimized to provide economizer control.. The return fan is modulated to stabilize building pressure at a slight positive. For simple supply and exhaust systems the building pressure and static pressure sensors may be connected directly to the frequency inverter with an internal PID controller.

Typical Energy Savings are realized from converting pneumatic (or electromechanical) control to DDC control with frequency inverter in the following ways:

  • Locking inlet guide valves mechanically open to allow the frequency inverter to fully modulate the fans.
  • Free cooling by accurately modulating the economizer dampers and sequencing the mechanical equipment.
  • Controlling static and resetting the static pressure during short periods of time.
  • Accurate building pressurization.
  • Implementing other energy saving measures which include supply air reset, and night purge routines.

CONTROL CONSIDERATIONS

  • Placement of the indoor static pressure sensor is important as it should provide a stable signal. Entrances, dock, and other areas where large , sudden static pressure changes may occur should be avoided.
  • The outside reference static tip should be shielded from wind and rain.
  • When the exhaust fan is frequency inverter controlled, consider a 2-position air damper to prevent the outside air from entering the building (infiltration) when the exhaust fan is off or a very low speeds.
  • For simple VAV systems, consider using frequency inverters with built in PID controls such as the Iacdrive frequency inverters.. This minimizes hardware and installation costs. Static sensors provide a 0-10vdc control signal directly to the frequency inverter.
  • Duct mounted static pressure sensor should be mounted 2/3 of the distance of the distribution system.

AQ: Why designing an ethernet network IP scheme?

Depends on the size of the network (# of devices planned on connecting), for medium to large corporate networks go 10.x, for home and small business 192.168.x, or to 172.16.x. I would think the IP plan would be looking at least 10 – 20 years out. Changing IP schemes is hard, especially on a controls LAN, you wouldn’t want to undertake this task to frequently. Also consider any routing / firewalling / DMZing that you may want to do between the controls LAN and the business network (ideally these are separated networks).

Here’s some things to consider:

Number of devices or potential devices on the network
You may want to use a Class A subnet when you have or will have a large number of devices or a Class C when you have or will have a small number of devices.

Amount of traffic
A large subnet will more likely expose devices to more traffic. A smaller network may be employed to segment and/or control the amount of data that must be handled by a device.

Security
A large network (e.g., Class A) network may be more difficult to restrict access to or exposure of devices.

Simplicity
A Class A network is a flatter architecture and may be simpler to manage because you don’t have to worry about routing, gateways, and/or firewalls as much. This has to be balanced with security and traffic issues though.

Others
There are other considerations too…

In my experience, connecting with the “business” side of things is not technically difficult with an appropriate firewall/router. However, I have often found that the political challenges are more difficult. I have often butted heads with IT folks who have a fortress mentality and don’t understand the constraints, limitations, restrictions, and special considerations needed for industrial control systems. Many times, the best solution is to have a well defined line of demarcation where the IT folks take care of their side and the control guys take care of the control side. Most IT folks are OK with that as long as they can quarantine the control side to their satisfaction.

When it comes to selecting the firewall/router, you will need to take into consideration the protocols passing through it. If it’s the nominal business protocols like http, ftp, rdp, ssh, etc., then any business class device will typically work. However, if industrial protocols like CIP, Ethernet/IP, or OPC will be passing through, you will need to confirm that the firewall/router supports them specifically. When making the link, the important thing is the type of packet filtering and address translation rules that are configured in the firewall router. The IT folks might be more happy if they can setup a VLAN just for the controls.

AQ: Rotary Tube Furnace Efficiency

There are many factors that govern the performance of rotary tube furnaces. A direct fired rotary unit has a potential for much higher thermal efficiency due to the direct contact of the hot gases with the material in process. Cement kilns are the most common large scale unit operation with direct fired units. Any articles you find on this will be helpful. Thermal efficiency can be estimated by dividing the inlet temperature minus the outlet temperature by the inlet temperature minus the ambient temperature in absolute scales either Rankine or Kelvin. Then there is the issue of co-current versus counter-current firing and heat recovery from the hot material and the exit gas for which standard designs are available. Indirect fired rotary kilns have heat transfer limitations due to the thickness and alloys needed for high temperature calcination >500 C. There is no simple way to measure the equivalent of the inlet and outlet temperatures on a direct fired unit. There are simply exit gas temperatures from each zone and an approximate shell temperature on the hot side of the shell which is lower than the zone exit gas temp. These are useful for control purposes and consistent operation. The higher the temperature the material requires to achieve conversion the higher the shell side fired temperature has to be to provide the delta T necessary to drive heat through the shell into the material zone.

Some materials further limit heat transfer by adhering to the inside of the shell and acting as an insulator! This requires trial and error application of “knockers” at the ends of the shell or sometimes internally secured chains that bang around and knock the adhering material loose. This is a potential nightmare as the learning curve to install chains so that the securing lugs and the chains themselves will stay attached for acceptably long service before failing and ending up in the take off conveying equipment with usual breakage and downtime is an uncertain one. From Perry’s one can find thermal efficiencies for indirect fired rotary’s given as less than 35%. The bed fill can be 10-30% depending on the heat demand of the material and the heat transfer limitations. You will want to have real time gas usage metering on the burners so that you know the theoretical energy input. From that you can subtract the theoretical heat needed to complete your reaction and compare that to the input to see how efficiently you have used the energy input.

The few large high temperature direct fired rotary kilns I have seen had view ports for measuring the local wall temperatures by optical pyrometer. It can be a challenge to get a protected thermocouple sheath down into the moving bed for an actual bed temperature and even just to hang it in the gas streams at the outlet or inlet area. See if you can contact cement kiln suppliers for some configurations of temperature sensing elements for your application. Bed fill effects on heat transfer are related to several parameters. Above ~500 C gas and refractory liner temperatures, the main heat transfer mode will be radiative as far as the surface of the bed material. Within the bed it will be conduction and some convection at the surface. A thin bed will reach max. temperature in shorter time, but this reduces through put for a given gas temperature. If you increase bed fill to increase production you will have to increase the firing temperature and the outlet temperature will probably increase lowering your thermal efficiency. This becomes a trade off between production rate and energy efficiency. Countercurrent firing usually maintains the highest driving force for heat transfer along the bed and gives the highest temperature of the bed just before exit of the bed material.

Perry’s may have a useful section on direct fired rotary kilns and lime or cement manufacturing references may help you as well. Please make sure lead emissions to air are properly captured

AQ: Low impedance fault

A low impedance fault is usually a bolted fault, which is a short circuit. It allows a high amount of fault current to flow, and an upstream breaker or fuse usually senses the high current and operates, ending the event. A high impedance fault, usually an arc fault, is a fault of too high of an impedance for overcurrent protection to detect and operate, so the fault exists for long period of time without tripping upstream protection. Examples of arc faults are: A high or medium voltage distribution utility wire falling to earth in a Y grounded system and arcing to earth where no breaker or fuse will clear; another example is any fault tracking through a substance such as cable insulation or even air….this could be wiring within a building wall with a fault that lasts long enough to ignite the building wall it is installed in, which happens all the time somewhere (sometimes called “arc through char”). Another high impedance fault is one within a transformer secondary coil, arcing through the coil insulation and transformer oil (oil cooled units)…the arc will boil the oil into component gases such as acetylene and hydrogen and if the arc fault lasts long enough and gets to the gases, the gases may explode…and the primary fuse protection will likely not detect this for some time. There are many other examples of high impedance faults. One way to tell a high impedance fault or arc fault is if there is a protecting breaker or fuse that did not operate for a fault…if the breaker or fuse are correctly sized and working properly and did not operate that usually indicates a high impedance fault….a short circuit usually generates high enough current to trigger breaker/fuse operations (assuming normal circuit impedance is low). Another way to look at it is any fault in a power circuit with an impedance such that less than “available” fault current flows.

AQ: Special Protection System Advantages and Disadvantages

Quite a few yrs. ago around 1988, I was a Protection and Control Engineer at a large utility in the SE. We were doing our planning to bring the final unit of a large 4 unit plant on line, when it was discovered that we could encounter some unusual instability scenarios. The funny thing was that with all units on-line and above a certain MW output, all that would need to occur would be opening of a remote 500kV breaker on one of the particular lines and the event could trigger, eventually bringing ALL 4 units at the plant out-of-step and tripping off all of the generation in just a few minutes (3600 MW).

The studies were performed numerous times by internal and external experts but the results were always the same. The key problem seemed to be the existing network configuration of 4 units and only 3 transmission lines. Adding a 4th 500kV line from the plant seemed to cure the problem under all conditions, including close in 3 phase faults with breaker failure. Unfortunately, the cost and timeline to build a new t-line was a real challenge!

In order to proceed with commissioning the 4th unit and remediating any scenarios for tripping all generation, a Special Protection System (SPS) was developed. A transfer trip channel was installed at the remote substation, keying on the breaker contact opening. At the plant, a Unit Trip scheme was installed that had a MW meter supervising tripping of any one unit selected by the plant operator (U1-U2-U3-U4). If all units were on line and generation was above 2500 MW (margin of safety added), then a receipt of remote breaker opening would trip the selected unit to avoid having all units cascade into out-of-step condition.

Advantages: Clearly, this Special Protection System saved the day, and bought time until an additional line was added 4 years later.

Disadvantages: The downside was the challenge of installing and testing such a complicated scheme with the potential for mis-operation. I don’t recall any mis-operations occurring, but it was still a bit “dicey”. I have been at that same plant during a full load unit trip (Generator differential) and it was an “exciting” experience to say the least! While I did recommend that we conduct a “live test” to see what would really happen and perhaps test our system BLACK START procedures, this suggestion was not well received by management (LOL).

This was my only encounter with such a special protection system scheme in my 35 years of utility work, but it was very interesting to be involved with this project.

AQ: Resistance to ground

Resistance to ground is greatly influenced by the ambient conditions and the state of the motor when tested.

Factors Affecting Insulation Measurement:
First, it is important to understand that we are measuring a motor circuit. We are connecting our test instrument at a point where we can measure the majority of the de-energized circuit. As such, we do not necessarily know where an insulation anomaly is located when identified. We also have the motor circuit potentially exposed to differing environments. Ambient temperature and humidity can have a significant effect on any insulation measurements. When a motor circuit’s insulation is tested is also a major variable. Testing a motor circuit immediately after shut down will most likely yield good results. This is because the motor is warm and dry. Testing a motor after it has been shut down for a while may indicate insulation problems, but if the motor is allowed to reach ambient temperature, the insulation integrity may appear normal. This is because while cooling, particularly in somewhat humid conditions, moisture (condensation) will accumulate within the motor and lessen ground resistance. Is this a problem? Yes, particularly if starting from a partially cooled state. Most motor failures occur during starting. This is when the insulation is exposed to the most stresses. If your motors are only down for a few hours at a time, then this is when insulation testing should be conducted.

When conducting insulation testing, the most important consideration is consistency. Always test at the same location, use the same test voltage, perform the test for the same amount of time, and use the same test instrument. It is also important to note the motor temperature, ambient temperature, and relative humidity. It is also helpful to compare like motors and the motors that are operating within the same environment.

Insulation testing is somewhat ambiguous. Although there are reference standards, they cannot be rigidly followed because they do not factor in all of the potential variables that may be encountered. Temperature is the biggest variable. Temperature of the motor and the ambient temperature are of primary concern. One method to help negate the influence of temperature is performance of a “Timed Resistance Test.” This testing is comprised of “Dielectric Absorption,” “Polarization Index,” and “Step Voltage” testing. Dielectric Absorption is a 1 minute test. The resultant values at 30 seconds and 1 minute are logged and the ratio of the 30 second value divided into the 1 minute value, is a relative indicator of insulation integrity. A polarization index is a 10 minute test with the resultant ratio derived from the 1 minute value divided into the 10 minute value.

So, if ground resistance is low after prolonged shutdown and it is at ambient conditions, then you probably have an insulation issue. Conditioning of the insulation may be required. A motor shop can perform a “Clean, Dip and Bake.” process which will prolong the motor longevity. If the motor is several years old you may want to HiPot the insulation but if you are not using one of the newer units that automatically shut down upon a jump in current, you may cause insulation failure and that would necessitate a rewind.

AQ: Negative sequence

Negative sequence will not cause a physical rotation. This component creates a field which, though not strong enough, tries to counter the primary field, An increase in this component will cause the motor to overheat due to the opposition. a physical rotation is not likely to occur.

Negative sequence currents are produced because of the unbalanced currents in the power system. Flow of negative sequence currents in electrical machines (generators and motors) are undesirable as these currents generates high temperatures in very short time. The negative sequence component has a phase sequence opposite to that of the motor and represents the amount of unbalance in the feeder. Unbalanced currents will generate negative sequence components which in turn produces a reverse rotating filed (opposite to the synchronous rotating filed normally induces emf in to the rotor windings) in the air gap between the stator and rotor of the machines. This reverse rotating magnetic field rotates at synchronous speeds but in opposite direction to the rotor of the machine. This component does not produce useful power, however by being present it contributes to the losses and causes temperature rise. This heating effect in turn results in the loss of mechanical integrity or insulation failures in electrical machines within seconds. Therefore it is undeniable to operate the machine during unbalanced condition when negative sequence currents flows in the rotor and motor to be protected. Phase reversal will make the motor run in the opposite direction and can be very dangerous, resulting in severe damage to gear boxes and hazard to operating personnel.

AQ: Synchronous generator operating frequency

When synchronous generators (alternators) are connected in parallel with each other on an AC grid, they are all operating at a speed that is directly proportional to the frequency of the AC grid. No generator can go faster or slower than the speed which is proportional to the frequency.

That is, when a synchronous generator and its prime mover is operated in parallel with other synchronous generators and their prime movers, the speed of all of the generator rotors (and hence their prime movers if directly coupled to the generator rotors) is fixed by the frequency of the grid. If the grid frequency goes up, the speed of all the generator rotors goes up at the same time. Conversely, if the grid frequency goes down, the speed of all the generator rotors goes down at the same time. It is the job of the grid/system operators to control the amount of generation so that it exactly matches the load on the system so that the frequency remains relatively constant.

Isolated or is landed generators that are not in parallel with other generators have an added limitation in that keeping exactly 50Hz is somewhat difficult, or puts too much demand on controlling/governing systems. In such environments it is normal to accept some small deviation from the nominal frequency.

The vast majority of power for industry is supplied by large rotating AC generators turning in synch with the frequency of the grid. The frequency of all these generators will be identical and is tied directly to the RPM of the generators themselves. If there is sufficient power in the generators then the frequency can be maintained at the desired rate (i.e. 50Hz or 60Hz depending on the locale).

An increase in the power load is accompanied by a concurrent increase in the power supplied to the generators, generally by the governors automatically opening a steam or gas inlet valve to supply more power to the turbine. However, if there is not sufficient power, even for a brief period of time, then generator RPM and the frequency drops.

By operating transformers at higher frequencies, they can be physically more compact because a given core is able to transfer more power without reaching saturation and fewer turns are needed to achieve the same impedance. However, properties such as core loss and conductor skin effect also increase with frequency. Aircraft and military equipment employ 400 Hz power supplies which reduce core and winding weight. Operation of a transformer at its designed voltage but at a higher frequency than intended will lead to reduced magnetizing current. At a lower frequency, the magnetizing current will increase. Operation of a transformer at other than its design frequency may require assessment of voltages, losses, and cooling to establish if safe operation is practical. For example, transformers may need to be equipped with ‘volts per hertz’ over-excitation relays to protect the transformer from overvoltage at higher than rated frequency.