Category: Blog

AQ: The basis of rating a NGR in electrical system

NGR stands for Neutral Grounding Resistor. When an earth fault current occurs on a plant, assuming that there is no external device presented to limit the earth fault current, the magnitude of the earth fault current is limited only by the earth impedance presented between the point of fault (to earth) and the return path (typically a star point of a transformer). If the earth impedance is low (type of soil being one of the reason amongst others), the fault current magnitude can be significantly high, and if left unchecked could damage the primary equipment. It is therefore mandatory that the earth fault current be limited to a suitable value, which is typically the rated value of the plant as a thumb rule. Why use the rated value? Because the plant has been designed to carry the rated current continuously.

Let’s take an example: say you have a transformer 60MVA, 132/33kV Star-Delta transformer. It is required to calculate the value of NGR to be connected to the zig-zag transformer on the 33kV Delta. the value of the resistor required to limit the earth fault current to the transformer’s LV rated value is (33 x 33) / 60 = 18.15 Ohms.

(Earth Fault current limited to rated value = (60 x 1000) / (1.732 x 33) = 1050A) When you go to a supplier you might find he supplies only 20 ohms resistor (as you might not get the exact value that you have calculated theoretically). No problem, use the 20 ohms and calculate what your new value of earth fault current would be (33 x 1000 / (1.732 x 20) = 952.6A, which is less than the transformer’s rated LV current. So you’re safe. This is how I would go about. In fact I would go a step further and introduce a safety factor of 20% i.e. I’ll bump up the value of the resistor from 20 ohms by an extra 20% and buy a resistor/ NGR of 1.2 x 20 = 24 ohms. So I am 100% sure that the earth fault current is way below the rated value and my transformer will be safe, even if the fault current goes undetected for any unforeseen reason say my earth fault protection has failed to pick up.

Make sure however that the earth fault setting that you choose is sensitive enough to pick up for the earth fault current calculated. I would generally put two relays a 64 or REF designed to pick up and operate instantly backed by a 51N with a sensitive setting but with a delay of a couple of seconds to pick up in case the 64 has failed to pick up.

So that’s it. I have described how I would go about calculating the earth fault current, selection of NGR value and how I would protect it.
Protection and related devices aiding protection don’t come cheap. Also I assume by your comment “this method is the most expensive option available since the cost of the transformer shall be astronomical”, you are referring to the Zig-Zag transformer and not the actual 132/33kV Star-Delta power transformer, under question.

I have taken a very generic example and tried to focus on how to arrive at a suitable value of an NGR, assuming an Star HV and Delta LV. My aim being to calculate how I could limit the fault current on the Delta LV. Being a Delta winding, I have to use a Zig-Zag transformer, for providing a low zero sequence path for the flow of earth fault current. It is really the Zig-Zag trafo. that bumps up the cost.

Note: If the above transformer is one of a kind, i.e. this is the only transformer in an isolated network, then I simply disregard the Zig-Zag transformer + NGR method and use the 3 PT broken delta method for 3Vo detection to drive a 59N. My cost here would be very low.

If the transformer is a Star-Star type with HV start solidly grounded, and LV star impedance (NGR) grounded, then I don’t need a Zig-Zag trafo. on the LV side. My cost is purely for the NGR alone.(Of course this transformer will have a Delta tertiary which may need it’s own protection depending on the whether one plans to load the tertiary or not. We could di

AQ: Difference between PLC and DDC system

PLC is defined as Programmable Logic Controller. It is a hardware, Includes processor, I/P & O/P Modules, Counters, Function Blocks, Timers,,, etc. The I/Os are either Analogue or Digitals or both. PLC can be configured to suit the application and to programmed in a logic manner by using one of the programing language such as Statement List, Ladder Diagram,, etc Interaction in real time between inputs and the resultant of the outputs through the program logic – PID – gives the entire Control System. While the Digital Control System I believe it is Software/ System that uses only Digital Signals for control and PLC/PC/Server/Central Unit may constitutes an Integral part of this system.

AQ: Power Transformer power losses

Power losses of ferromagnetic core depend from voltage and frequency. In case where is no-load secondary winding, power transformer has a power losses in primary winding (active and reactive power losses) which are very small, due to low current of primary winding (less than 1% of rated current) and power losses of ferromagnetic core (active and reactive power losses) which are the highest in case of rated voltage between ends of primary winding…

Of course, we can give voltage between the ends of primary winding of power transformer (voltage who is higher from rated voltage), but we need include some limits before that:

1. if we increase voltage in the primary winding of power transformer (voltage who is higher from rated voltage), we need to set down frequency, otherwise ferromagnetic core of power transformer will come in area of saturation, where are losses to high, which has a consequence warming of ferromagnetic core of power transformer and finally, has a consequence own damage,

2. if we increase voltage in the primary winding of power transformer (voltage who is higher from rated voltage), also intensity of magnetic field and magnetic induction will rise until “knee point voltage”: after that point, we can’t anymore increase magnetic induction, because ferromagnetic core is in area of saturation…

In that case, current of primary winding of power transformer is just limited by impedance of primary winding… By other side, in aspect of magnetising current, active component of this current is limited by resistance of ferromagnetic core, while is reactive component of this current limited by reactance of ferromagnetic core.

There is a finite amount of energy or power that can be handled by various ferromagnetic materials used for core material. Current increases greatly with relatively small voltage increases when you are over the knee of the magnetization curve characterized by the hysteresis loop. Nickel/steel mix materials saturate at lower flux densities than silicon steel materials. 50ni/50fe materials saturate at about 12kG; 80Ni/20Fe as low as 6kG. Vanadium Permendur material saturates at levels as high as 22kGauss- Nano-crystallines- 12.5kG (type), Ferrites -typically over 4kG at room, decreasing as temperature rises. What causes saturation?: Exceeding material limits.

AQ: What is ANSYS software?

This is a finite element analysis tool for various applications.
In power we get the voltage (stress) distribution in equipment like cables, bends in cables etc including stator winding of generators.

Once you go deep into it the applications become more apparent.  In mechanical engineering using FEM you can identify the stresses in each member of the structure and so on.

I believe ANSYS, Abacus, Nashtran etcare extensively used for detailed analysis of stresses including electrical stresses. Some of the above offer introductory courses on line.
One needs extensive and considerable insight into partial differential equations and advanced mathematics.

AQ: Transmission line low voltages and overload situations

Q: I want to know just what the surge impedance loading (SIL) is but its relevance towards the improvement of stability and reliability of a power network especially an already existing one with various degrees of low voltages and overload situations?

A: The surge impedance loading will provide you with an easy way of determining if your transmission line is operated as a net reactor (above SIL, so external sources of (2) line-voltage-drop limitation
(3) steady-state-stability limitation

In contrast with the line voltage drop limitation, the steady state stability limitation has been discussed quite extensively in the technical literature.

However, one important point is rarely made or given proper emphasis; that is, the stability limitation should take the complete system into account, not just the line alone. This has been a common oversight which, for the lower voltage lines generally considered in the past, has not led to significant misinterpretations concerning line loadability

At higher voltage classes such as 765 kV and above, the typical levels of equivalent system reactance at the sending and receiving end of a line become a significant factor which cannot be ignored in determining line loadability as limited by stability considerations, so surge impedance loading plays a fundamental role in reliability and stability.

AQ: Transformer Saturation

AQ: Flashover in busbars

As for XLPE cable testing, if XLPE is used for insulation in the switchgear, the cross linking will be treed by HV DC and permanently destroyed. For this reason, HV DC is no longer used for XLPE cable testing. The switchgear should have a power frequency withstand test only and not HV DC. Refer to the relevant switchgear standard for the applied rms voltage. Any XLPE insulation will need to be replaced as it is most likely has been damaged by treeing of the cross linkages in the insulation. A maximum of say 2.5 kV DC is allowed for IR and PI only.

Humidity plays important part in flashover. We faced a problem of flashovers in Air insulated 11kV Switchgear busbar compartments in rainy seasons. Any sharp edge will ionize the surrounding air, which becomes conductive to high voltage discharge. Moisture will hasten the process of discharge. During HV test also this aspect should be kept in mind.

And make sure the following:
Clean all the supporting bus insulators and spouts with CRC spray.
Ensure the earth bus continuity and its connection with the earth grid.
all PTs are taken out.
all CT ckt output shorted at the panel.
All LAs are disconnected
Conduct a general cleaning of busbars through CRC-sprays.
Megger the bus bar with 5KV between phases, and between phase to earth for 1 mints before HV test.
Ensure the earth bus continuity and its connection with the earth grid.
Use AC high voltage test preferably
Connect HV test kit body ground to the SWGR body ground.
Apply 80% of the power frequency voltage applied at the FAT test.
If you are doing with AC hv kit then this may be a larger unit and leakage current is exceeding and tripping.
Try for smaller sections of busbars/increase the leakage current if options are available.
Rate of rise of voltage should be in steps of 2KV/s and gradual.
Check tripping function of the test kit.
Apply voltage betweenL1-(L2+L3)=G-1mints
apply voltage in the same way between other phases also.
If it withstands ok alternately you have to go for individual inspection of the insulators/spouts.

AQ: What is the surge impedance load

The surge impedance loading (SIL) of a line is the power load at which the net reactive power is zero. So, if your transmission line wants to “absorb” reactive power, the SIL is the amount of reactive power you would have to produce to balance it out to zero. You can calculate it by dividing the square of the line-to-line voltage by the line’s characteristic impedance.

Transmission lines can be considered as, a small inductance in series and a small capacitance to earth, – a very large number of this combinations, in series. Whatever voltage drop occurs due to inductance gets compensated by capacitance. If this compensation is exact, you have surge impedance loading and no voltage drop occurs for an infinite length or, a finite length terminated by impedance of this value (SIL load). (Loss-less line assumed!). Impedance of this line can be proved to be sqrt (L/C). If capacitive compensation is more than required, which may happen on an unloaded EHV line, then you have voltage rise at the other end, the ferranti effect. Although given in many books, it continues to remain an interesting discussion always.

The capacitive reactive power associated with a transmission line increases directly as the square of the voltage and is proportional to line capacitance and length.

Capacitance has two effects:

1 Ferranti effect
2 rise in the voltage resulting from capacitive current of the line flowing through the source impedances at the terminations of the line.

SIL is Surge Impedance Loading and is calculated as (KV x KV) / Zs their units are megawatts.

Where Zs is the surge impedance….be aware…one thing is the surge impedance and other very different is the surge impedance loading.

AQ: Motor connection

Many years ago I had an experience of 4nos 37kW fin-fan motors wrongly connected at site to a star. After running for almost 1 year, the operators reported these motors were very warm and felt unusual. We removed one of them to the workshop and opened for inspection. All windings were OK but the rotor lamination surface had turned to light blue colour which showed a sign of abnormal heating.

I asked different experts in the industries for advices. From the advices, we suspected the motor could be designed for a delta connection even though the nameplate indicated a Star connection for 415V. We contacted the motor manufacturer by quoting the motor serial no. The manufacturer confirmed that the motors were designed for delta connection at 415V. The manufacturer apologized for the error in nameplate and gave us a free spare motor.

One clear sign that could lead us to believe that the motor was in a wrong star connection instead of delta was, for a 2 or 4-pole motor the no load running current should be more or less around 30% of FLC. When we tested run the motor in the workshop, the no load current was less than 15%xFLC.

After the rectification of all the 4 motors to delta connection, we had no complaint anymore. It was a good lesson out of this solved problem.

AQ: Difference between DCS and RTU

DCS distributed control system: you can control the system within a certain given facility from different locations, either control room or other places, and you should keep in mind this facility could be a in several locations but yet, hard-wired interconnected. while
RTU (remote Terminal Unit): you can control the system remotely through internet or a secure satellite connection which in not recommended for sensitive operations/process but it is ok for stand alone and not crucial systems. and more.

DCS as part of SAS (Substation Automation System) is based on local control of relays, meters and switchgear and automation as per required logic and programs that could be hardwired for serial protocols (like DNP 3.0) or through fiber optic when UCA 2.0 or IEC 61850 protocols are used.
For RTU, it’s just interface between substations’ I/O signals and dispatching center (SCADA) through communication links and specific protocols (such as IEC 101,104, Indactic, DNP 3.0, etc.). In other words, RTU has no controlling role by itself, but DCS as part of SAS has all programmed control logic within substations and without even connecting to dispatching center.

For Electrical Network Distribution, a System is required for controlling, Load dispatch as well as monitoring. Therefore Distribution Management System (DMS) or DCS to be adopted as an integrated System. They are simply like SCADA. Composed from Hardware, software, interfacing means & communication media / protocol as indicated above.
RTU (remote Terminal Unit) include Processor and all the required interfacing facilities as well as I/O(s) Modules.

The brief description of such system may be as follows:
The Substation prescribed Signals (MV switchgears, Transformer, Substation Auxiliary Equipment, etc.) to be hardwired to a marshaling box to Interface Cubicle where RTU located, RTU to be patched to the interface plate. Via the selected media “say FOC” the signals will be transferred to the DMC/DCS Control Centre. Accordingly, the real time status of the NW can be monitored and controlling can be achieved from remote.

The aforesaid Signals to be listed and sorted as per the required application to facilitate system configuration, integration and programming (unique address, function, type, is it required for control, monitor or both, which is digital & which is analogue, etc.).